Scope:

  • Conversion of existing plant room into a hygienic, food-safe production facility for meat processing
  • Formation of multiple controlled environments ranging from ambient to -4°C
  • Installation of IPN insulated panel system throughout (internal & external walls, ceilings, and liners), including:
    – 742 m² of 100mm chiller panels
    – 460 m² of 100mm ceiling panels
    – 154 m² of 50mm liner panels
    – 75 m² of 125mm external food-safe panels
  • Integration of full door package including chill/freezer personnel doors, sliding freezer doors, GRP double-action doors, and rapid-rise roller doors
  • Installation of supporting hygienic finishes including 250 m² chequer plate, 1,500 lm of flashings/trims, and 8,000+ fixings
  • Coordination of all works within a constrained and irregular existing structure, with enabling works completed in advance to maintain programme and avoid disruption to live operations.

 

End User: Storelogs

Division: Temperature Controlled

Completion: August 2025